Construction of the Production Test Facility at the Florence Copper site is continuing and progressing well

March 20, 2018

Currently, five drill rigs are now working 24/7 on the Florence Copper property to install injection and recovery wells, monitoring wells, and replacement irrigation wells. In addition, construction of the SX/EW facility is well underway. We expect production of our first copper cathode in latter part of this year.
Five drill rigs are now working 24/7 on the Florence Copper property to install injection/recovery wells, monitoring wells, and other needed wells for the PTF
The first concrete pour for the Florence Copper Solvent Extraction and Electrowinning Process Plant (SX/EW).