Subscribe:
Search: July 03, 2009    Home    HD    Site Map


Show printable version of 'Gibraltar' item in a New WindowEmail 'Gibraltar' item to a friend

Gibraltar

Photo Gallery
Gibraltar - Taseko's Foundation for Growth

A key component of Taseko's growth strategy is the expansion and modernization of its wholly owned Gibraltar mine. The goal is to create an operation with a mid-tier cost profile that is able to generate positive cash flow at all points of the copper price cycle.

Mine Expansion

Gibraltar is undergoing a major, multi-phase expansion and modernization program. Over the last two year, approximately $250 million has been invested at Gibraltar in both mining equipment and concentrator upgrades. By the end of 2009, Gibraltar's annual production capacity will increase to 120 million pounds of copper and 1.4 million pounds of molybdenum.

The Phase I & II expansion and modernization program includes the addition of a new 34 foot semi-autogenous grinding (SAG) mill, a complete replacement of the original flotation recovery system as well as a number of downstream upgrades and modifications.

Phase I was completed, on time and on budget, in early 2008 and the new equipment is being commissioned with ramp up continuing through 2009. During the ramp up, production levels are expected to steadily increase with expected annualized capacity reaching 100 million pounds of copper. Total cost for the Phase I expansion was $76 million.

Phase II modifications will allow the new SAG mill to process up to its designed capacity of 55,000 tons per day (tpd) by increasing capacity in other circuits in the concentrator. The expansion project will include the addition of an upgraded tailings pumping system, increased regrind capacity, cleaner flotation cells, pressure filters and driers. Phase II is targeted for completion in early 2010. Commissioning and ramp up of Phase II is expected to take place in the first half of 2010 until annualized production rates of 120 million pounds of copper are achieved. Approximately $20 million is left to spend on Phase II.

There are very few mining companies that have the ability to add incremental capacity at such a low capital cost and within such a short timeframe.

Extending Mine Life

Over the past three years, Taseko has spent in excess of $20 million to expand reserves and resources. When Gibraltar was restart in 2004, the proven and probable reserves were 149 million tons and the mine life was 12 years. Today, the mine life is 25 years following the most recent reserve update in December 2008.

The current Reserves and Resources are detailed below:

Gibraltar Reserves and Resources at September 30, 2007

Category
(at 0.20% Cu Cut-off)
Size (Million Tons) Grade Recoverable Metal Contained Metal
Cu (%) Mo (%) Cu (Billions lbs) Cu (Billions lbs)
P&P Reserves 472 0.315 0.008 2.7 3.0
M&I Resources 959 0.298 0.008 - 5.7


Operations

The following table is a summary of the operating statistics for fiscal 2008 compared to fiscal 2007.

Fiscal
20081
Fiscal
2007
Total tons mined (millions)² 51.8 35.4
Tons of ore milled (millions) 13.6 9.5
Stripping ratio 2.7 2.6
Copper grade (%) 0.351 0.328
Molybdenum grade (%MoS2) 0.009 0.011
Copper recovery (%) 75.8 77.5
Molybdenum recovery (%) 31.8 29.6
Copper production (millions lb) 76.9 51.8
Molybdenum production (thousands lb) 840 580
Copper production costs, net of by product credits³, per lb of copper US$1.87 US$1.03
Off property costs for transport, treatment (smelting & refining) & sales per lb of copper US$0.43 US$0.35
Total cash costs of production per lb of copper US$2.30 US$1.38


1 Fiscal 2008 relates to the 15 months ending December 31, 2008.

2 Total tons mined includes sulphide ore, oxide ore, low grade stockpile material, overburden, and waste rock which were moved from within pit limit to outside pit limit during the period.

3 The by-product credit is based on pounds of molybdenum and ounces of silver sold. Unit costs were lower in fiscal 2005 because molybdenum prices and pounds of copper produced were higher.

Site Statistics

The Gibraltar mine site covers approximately 109 square kilometers and consists primarily of 251 mineral claims and 30 mining leases. The property hosts resources and reserves in seven separate mineralized zones which has supported mining for most of the past 30 years.

Gibraltar is located in an area with well-developed infrastructure. The property is accessible by a combination of highways and paved roads, and it is close to a rail network that provides service for shipment of copper concentrates through the Pacific Ocean port of North Vancouver. The mine is a 45-minute drive from local communities that provide goods, services and personnel.

Forward Looking Statements

The above information includes certain statements that may be deemed "forward-looking statements". Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking statements. For more information on the risks inherent in the Company's business, Investors should review the Company's annual Form 20-F filing with the United States Securities Commission and its home jurisdiction filings that are available at www.sedar.com.